When Meta selected a site in Louisiana for its largest data center to date, it signed a deal with Entergy to power the site ...
(Reuters) -Entergy's Louisiana unit received approval from the Louisiana Public Service Commission to move forward with ...
4h
Cryptopolitan on MSNMeta’s $10B Louisiana data center plans receive state approval
Meta’s $10 billion Louisiana data center has received regulatory approval from the Louisiana Public Service Commission.
Louisianas Public Service Commission approved Entergys proposal to build three combined-cycle gas turbines and supporting transmission infrastructure to power Metas $10 billion AI data center in ...
The Louisiana Public Service Commission voted 4-1 to approve Entergy’s plan to build three natural gas power plants for Meta’s $800M data center in Richland Parish ...
State utility regulators approved a plan Wednesday to install three natural-gas fueled power plants for the tech company Meta, which needs the electricity for a massive data center it’s building in ...
2hon MSN
Louisiana officials approve $10 billion Meta AI facility as questions about electricity costs remain
Estimates suggest that the AI center will need roughly three times the amount of electricity that the city of New Orleans uses in a year ...
The facility is set to require more than double the energy needed to power the entire city of New Orleans during peak summer heat.
The Louisiana Public Service Commission gave Entergy the green light to construct three power plants in preparation for the ...
WGMB/WVLA Baton Rouge on MSN21h
Entergy plants approved for META data center
The Louisiana Public Service Commission is approving several Entergy projects that are supposed to ramp up power generation ...
The Louisiana Public Service Commission (LPSC) has given the go-ahead for the installation of three natural gas turbines set to power Meta’s planned 2GW data center in Richland Parish, Louisiana.